Installation instructions
Digging
Digging must ensure the necessary space for the manhole in both vertical &
horizontal directions. According to the terrain type the hole can be digged with vertical
walls or inclined embankment.
Stuffing
The tank must be placed on a compacted sand layer of minimum 10 cm.
After connecting the drainage network pipes proceed with the fill up of the hole.
Filling is realized with sand layers of maximum 15 cm all around the manhole body,
each layer compacted separately.
Minimum compacting grade must be 85%.
In green environment the sand layer upon the manhole can be 80% compacted. |